Up to $5,250/Year Tax-Free for Employee Training

Employers can offer GovCon training as a tax-free benefit. Almost free training for your team. Click to learn more →

All Guides

Stop Work Orders: What Contractors Need to Know

A stop work order can halt your contract performance immediately. Understanding your rights and proper procedures protects your business and cost recovery.

7 min read8 sections

What Is a Stop Work Order?

A Stop Work Order (SWO) is a written order from the contracting officer directing the contractor to stop all or part of the work under a contract.

Key characteristics:

  • Must be in writing from CO
  • Can be partial or complete work stoppage
  • Temporary — up to 90 days typically
  • Government responsible for increased costs

FAR clause:

FAR 52.242-15 (Stop-Work Order) governs SWOs in fixed-price contracts.

Why government issues SWOs:

  • Funding issues
  • Requirements changes
  • Investigations or audits
  • Technical problems
  • Protests affecting the contract
  • Administrative needs

Important distinction:

  • Stop work order — Temporary suspension, work expected to resume
  • Termination — Contract ending (for convenience or default)

Responding to a Stop Work Order

Immediate actions:

  1. Verify authority — Confirm order is from contracting officer
  2. Understand scope — Which work is stopped?
  3. Acknowledge receipt — Written acknowledgment
  4. Stop the work — Comply with order
  5. Preserve evidence — Document status at stop point

Documentation to maintain:

  • Copy of stop work order
  • Work status when order received
  • Costs incurred to stop point
  • Ongoing costs during stoppage
  • Personnel affected
  • Subcontractor impacts

What you should NOT do:

  • Ignore the order
  • Continue work without authorization
  • Wait to document impacts
  • Assume it will resolve quickly

Protective steps:

  • Minimize ongoing costs
  • Take reasonable steps to protect work in progress
  • Notify subcontractors
  • Begin tracking stop-work costs

Cost Implications

Recoverable costs:

Under FAR 52.242-15, contractor may recover reasonable costs resulting from the stop-work order:

  • Idle labor and equipment
  • Material storage and preservation
  • Subcontractor stop-work costs
  • Demobilization and remobilization
  • Schedule impacts
  • Extended overhead

Cost tracking requirements:

  • Separate accounting for stop-work costs
  • Document link to stop-work order
  • Track both direct and indirect impacts
  • Keep contemporaneous records

Mitigation requirement:

  • Take reasonable steps to minimize costs
  • Reassign personnel if possible
  • Don't incur unnecessary costs
  • Document mitigation efforts

Unrecoverable costs:

  • Lost profit on stopped work (typically)
  • Costs not properly documented
  • Costs that could have been avoided

Get the Cheat Sheet

Join 5,000+ GovCon professionals. Get weekly insights and free templates.

No spam. Unsubscribe anytime.

Duration and Expiration

Standard duration:

FAR 52.242-15 limits stop-work orders to 90 days unless extended.

Before 90 days expires, government must:

  • Cancel the stop-work order and resume work, OR
  • Extend the stop-work order (requires your consent for certain costs), OR
  • Terminate the contract

If order exceeds 90 days without action:

  • You may request cancellation
  • If denied, treated as termination for convenience
  • Full T4C cost recovery available

Extensions:

  • Government may extend with written modification
  • You're not obligated to agree
  • Negotiate continued cost recovery

Tracking deadlines:

  • Mark 90-day expiration date
  • Send reminder to CO before expiration
  • Document all communications

Resumption of Work

When stop-work order is cancelled:

Contractor resumes work under adjusted terms.

Equitable adjustment:

  • Request adjustment within 30 days of resumption (per FAR)
  • Cover increased costs from stop-work period
  • Adjust delivery schedule if affected
  • Document all impacts

Elements of adjustment:

  • Stop-work period costs
  • Remobilization costs
  • Schedule extension
  • Impact on remaining work

Resumption challenges:

  • Personnel may have been reassigned or departed
  • Subcontractors may have moved on
  • Material costs may have changed
  • Learning curve to restart

Documentation for REA:

  • All stop-work period costs
  • Schedule impact analysis
  • Remobilization estimates
  • Effect on remaining work cost

See: Contract Modifications Guide

Stop Work vs Other Suspensions

Stop work order (FAR 52.242-15):

  • Fixed-price contracts primarily
  • Up to 90 days
  • Contractor cost recovery
  • Specific clause governs

Suspension of work (FAR 52.242-14):

  • Construction contracts
  • Different procedures and timeframes
  • Similar cost recovery concept

Government delay of work (FAR 52.242-17):

  • Applies to supply/service contracts
  • Government-caused delays
  • Equitable adjustment available

Informal work stoppages:

  • Verbal direction to slow/stop
  • Should be documented
  • May be constructive stop-work
  • Same cost recovery principles

Know your clauses:

Check which clauses are in your contract — they determine your rights and procedures.

Subcontractor Considerations

When you receive a stop-work order:

  • Notify subcontractors immediately
  • Issue corresponding stop-work to subs
  • Document subcontractor costs
  • Include sub costs in your recovery

Subcontract clauses:

  • Should have stop-work provisions
  • Flow down government contract terms
  • Protect your ability to recover

Subcontractor impacts:

  • May have committed resources
  • May have limited ability to reassign
  • May have different cost structures
  • Must provide documentation for recovery

Communication:

  • Keep subs informed of status
  • Coordinate resumption planning
  • Get cost data for REA
  • Document everything in writing

Best Practices

Preparation (before it happens):

  • Know your contract clauses
  • Have stop-work procedures ready
  • Ensure subcontracts have appropriate provisions
  • Train project personnel on procedures

When order is received:

  • Immediate written acknowledgment
  • Establish separate cost accounting
  • Document work status at stop point
  • Notify all affected parties
  • Begin cost tracking immediately

During stop-work period:

  • Minimize costs where reasonable
  • Maintain documentation
  • Track timeline toward 90-day limit
  • Communicate with CO on status
  • Prepare for either resumption or termination

At resumption or termination:

  • Submit REA within required timeframe
  • Include all documented costs
  • Request schedule adjustment if applicable
  • Follow up to ensure timely resolution

See: Contract Disputes Guide if issues arise

Frequently Asked Questions

Q:Can anyone issue a stop work order?

No. Only the contracting officer (CO) can issue a valid stop-work order. If someone else directs you to stop work, ask for written confirmation from the CO. Document verbal directions and request written confirmation.

Q:Do I get paid during a stop-work order?

You can recover reasonable costs incurred during the stop-work period through an equitable adjustment. This typically includes idle labor, equipment, storage costs, and other direct impacts. Lost profit is generally not recoverable.

Q:What if the stop work order lasts more than 90 days?

You can request the order be cancelled. If the government doesn't cancel it, you may treat this as a termination for convenience and pursue full T4C cost recovery.

Q:Can I refuse a stop work order?

No. You must comply with a valid stop-work order from the CO. Continuing work without authorization could jeopardize your cost recovery rights and create other problems.

Q:How do I document stop work costs?

Set up separate cost tracking immediately. Document idle labor hours, equipment standby, material storage, subcontractor impacts, and any other direct costs. Keep time records, receipts, and contemporaneous notes.

Q:What's the difference between stop work and termination for convenience?

Stop work is temporary suspension — work is expected to resume. Termination for convenience ends the contract permanently. If a stop work exceeds 90 days without resolution, it converts to T4C.

Q:Can I reassign workers during a stop work?

Yes, and you generally should when possible. The government expects you to mitigate costs. However, you can recover costs associated with disruption and any premium costs to bring workers back.

Q:How long do I have to submit a claim after resumption?

FAR typically requires a request for equitable adjustment within 30 days after resumption of work. Don't wait — submit promptly with complete documentation.

Handle Contract Disruptions

Stop work orders and other contract disruptions require careful management to protect your rights and recover costs. Our team helps you navigate complex contract situations.

Get Contract Help

Land a High-Paying GovCon Role

Jobs that use the skills from this guide

Continue Learning